Key takeaways

  • The Act on Facilitation of Licensing and Public Services B.E. 2569 (unofficial translation) was published in the Government Gazette on 8 July 2026 (Vol. 143, Part 38 Kor) and repeals the 2015 Act. It comes into force 180 days after publication, which government agencies state is 4 January 2027. Chapter 1 (General Provisions) has applied since publication.
  • It covers every licence, registration and notification that requires an application to a state agency (Section 4). Section 6 lists exclusions, including court proceedings and criminal justice.
  • Once an application and its documents are complete under the agency's public manual, the officer may not ask for further documents or reject the application as incomplete (Section 15). The agency must decide within the time stated in the manual and, if it does not, must give reasons for the delay every 15 days (Section 18).
  • A licence for a continuing business may be renewed by paying the renewal fee instead of filing an application (Section 20).
  • Deemed approval, main and secondary licences, and minimum five-year licence terms do not start automatically on 4 January 2027. Each needs a Royal Decree naming the licence (Sections 19, 21 and 22).

1. What the Act provides

TopicRuleSection
Public manualMust state criteria, fees, steps, time limits, the document list and guidance on discretion, and must allow electronic filing14
Checking the applicationChecked and answered at once; electronic applications checked by the next working day; no further documents once complete15 and 16
Time limitDecision within the manual's time limit, notified within 7 days; reasons for delay every 15 days18
RenewalPayment of the fee replaces the application; where the specific law sets no renewal fee, the licensee may keep operating after applying until a non-renewal order is issued20
Documents the state already holdsRules must not require documents the agency itself issued or already has11
Change of rulesNew criteria do not apply to applications already lawfully filed, unless a law provides otherwise12
LanguageAgencies may issue forms, licences and manuals in English and allow them to be completed in English36

2. What applies from when

ProvisionApplies from
Chapter 1, General Provisions (Sections 8 to 13)8 July 2026
The rest of the Act4 January 2027
Deemed approval (Section 19)When a Royal Decree names the business and the licence
Main and secondary licences (Section 21)When a Royal Decree is issued
Extension of licence terms to at least five years (Section 22)When a Royal Decree is issued
Detailed rules on renewal by fee paymentUnder a Ministerial Regulation; until then the Royal Decree under the 2015 Act continues (Section 39)
Fast-track channel for an extra fee (Section 35)Under a Ministerial Regulation; existing channels may continue (Section 40)

3. What to do now

  • Build a register of the company's licences, with the governing law, expiry date and renewal method for each.
  • Download the current public manual for each licence and note the review period it states.
  • File complete applications and keep the completeness record, or the deficiency record, signed by the officer.
  • Diarise the end of the review period. If it passes, ask for the written reasons for the delay.
  • Do not start operating on the basis of deemed approval unless a Royal Decree covers that licence.

4. What the Act leaves open

The Act does not say which licences will have deemed approval. The author found no confirmation that any Royal Decree under Section 19, 21 or 22 had been issued at the time of writing. The Ministerial Regulations on renewal and on the fast-track channel are still to be followed. The Central Application Centre under Section 30 depends on a Cabinet decision. Some permissions under environmental law may be excluded as determined by the Public Sector Development Commission (Section 6).

Practitioner's note

From filing and renewing licences for foreign-invested companies, three points are worth using. The first is the Section 15 record. Once the officer records that an application is complete, the agency cannot come back for more documents, so a company should ask for a copy of that record every time. The second is Section 12. If an agency changes its criteria while an application is pending, the application is still assessed under the earlier criteria, so the filing date matters. The third is expectations. The provision that attracts the most attention, deemed approval, cannot be relied on until a Royal Decree is issued. A company planning to open a factory or a branch in 2027 should still allow the time stated in the current manual. For the main licences foreign investors need, see Louis Group's guide The Complete Guide to Establishing Your Business in Thailand for Taiwanese Companies 2026: Understanding BOI, IEAT, and FBL at a Glance .

Sources

Frequently asked questions

When does the Act take effect?

It was published in the Government Gazette on 8 July 2026 and comes into force 180 days later, which government agencies state is 4 January 2027. Chapter 1 and the second paragraph of Section 38 have applied since publication.

If the agency misses its deadline, is the licence automatically granted?

Not in every case. Deemed approval applies only to the businesses and licences named in a Royal Decree, and only to activities that are not high-risk. For other licences the agency must give reasons for the delay every 15 days.

Do we still have to file a renewal application?

It depends on the licence. A continuing business may pay the renewal fee instead of applying. High-risk activities may be excluded by Ministerial Regulation, and the rule does not apply to permissions granted for a single occasion.